Hearings & Deadlines

2024 Planning Board Hearings

Hearing Date

Deadline

January 24, 2024

December 27, 2023

February 21

January 17

March 20

February 22

April 17

March 18

May 15

April 17

June 12

May 15

August 21

July 17

September 18

August 21

October 16

September 18

November 20

October 23

December 18

November 20

January 17, 2025

December 20, 2024

The above dates are subject to change. 

All applications are due by noontime on the deadline date.  Otherwise, the application will be heard at the next ZBA hearing.

Plan Submission Deadlines

All applicants submitting Subdivision and Site Plans undergoing the first review from the town consulting engineer will need to ensure plans are received by Stantec by the first Wednesday of the month, in order to be heard at that month’s public hearing.  Applicants are still subject to the timelines outlined in Section 3.07 of the Auburn Subdivision and Site Plan Regulations.

Subdivision and Site Plans undergoing secondary review from the town consulting engineer will need to be received by Stantec and the town by the second Wednesday of the month, in order to be heard at that month’s public hearing.

If plans are not received on time, which is by Noontime on the application deadline date, the hearing will automatically be continued and the appointment deleted from the agenda.  The Planning Board shall not consider any action on the project during the hearing.